The Supreme Court has quashed land acquisition proceedings initiated for mining operations by Dalmia Cement Bharat Limited in the Sundargarh district of Odisha, ruling that the process violated mandatory provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. A Bench comprising Justice Satish Chandra Sharma and Justice Deepankar Datta delivered the judgment on November 19, 2026, in Civil Appeal No. 8294 of 2026, Bibol Toppo and Others vs State of Odisha and Others. The appeal was filed by residents of Kukuda, Bihabandha and Lanjiberna villages challenging the Orissa High Court judgment dated September 6, 2024, which had upheld the acquisition.
What were the key statutory violations identified by the Supreme Court in the Lanjiberna land acquisition?
The Court held that the government failed to obtain the mandatory prior consent of at least 80 per cent of affected families as required under Section 2(2)(b) of the 2013 Act before examining the acquisition proposal. It further ruled that the land fell within a Scheduled Area, making prior consent of the concerned Gram Sabhas mandatory under Section 41(3) of the Act. The Gram Sabhas had rejected the acquisition through resolutions passed on January 26, 2020, yet the authorities proceeded despite the opposition.
Procedural violations and expert group composition
Beyond the absence of consent, the Bench identified serious procedural irregularities. The Court noted that no public hearing was conducted on the Social Impact Assessment report, a mandatory step under the statutory framework. Additionally, the Expert Group constituted to independently evaluate the Social Impact Assessment included a person connected with Dalmia Cement, compromising the independence of the evaluation process. The Court emphasised that the requirement of Gram Sabha consent cannot be reduced to a mere formality and that community participation is a substantive right in Scheduled Areas.
Comparison of statutory requirements and compliance
Statutory Provision | Requirement | Compliance Status |
|---|---|---|
Section 2(2)(b), LARR Act 2013 | Prior consent of 80% affected families for private company acquisition | Not obtained |
Section 41(3), LARR Act 2013 | Prior consent of Gram Sabhas in Scheduled Areas | Not obtained; Gram Sabhas passed resolutions opposing acquisition on Jan 26, 2020 |
Social Impact Assessment Rules | Public hearing on SIA report | Not conducted |
Expert Group Composition | Independent evaluation of SIA | Compromised; included person connected with Dalmia Cement |
Operative outcome and directions
The Supreme Court allowed the appeal, quashed the acquisition proceedings and all related notifications and orders, and set aside the Orissa High Court judgment dated September 6, 2024. The Court clarified that the authorities are at liberty to initiate a fresh land acquisition process in accordance with the law and the findings recorded in the judgment. The dispute concerned the proposed acquisition of 273.57 acres of agricultural land to enable Dalmia Cement to exercise surface rights for mining operations, although the company already held mining rights over the area. The land continued to belong to its respective owners throughout the proceedings.
Significance for tribal communities in Scheduled Areas
The ruling reinforces statutory safeguards governing land acquisition in Scheduled Areas, particularly the primacy of Gram Sabha consent and the procedural integrity of Social Impact Assessments. The judgment affirms that tribal land rights and livelihood protections under the 2013 Act must be respected in acquisition proceedings, including those undertaken for private mining projects. The affected communities had pursued the legal challenge for six years. Fr Ashok, who supported the villagers throughout the litigation, described the verdict as a victory for justice after sustained efforts, noting that the entire land acquisition had been quashed and the High Court judgment set aside.